£100K Saved for client in site clear up
Case Study: Great Baddow, Chelmsford
Disposing of harzardous waste is a very costly business, so encountering unexpected volumes of hydrocarbon contaminated soils can lead to substantial abnormal development costs.



Sustainable solution for legacy of former gas works
Case Study: New Haddo Estate, Greenwich
The regeneration of the New Haddo estate by our client, Bellway plc, required remediation work to remove substantial in-ground obstructions and to treat some 7,000m³ of coal tar contaminated fill/soils.



Successful remediation of a challenging and commercially risky site
Case Study: Pitwines, Poole
Pitwines Gas Works is located 300m from Poole Harbour, a Site of Special Scientific Interest. Our client Crest Nicholson wanted to develop 504 residential units on an area of 5 hectares but needed to protect the groundwater receptor (the harbour) by addressing both the source contamination on site and pathway contamination issues.